Scenario guide

Agency Utilization and Target-Margin Project Quotes

Connect billable capacity with project quotes that recover labor, contractor costs and allocated overhead.

How to use these calculators

A service business cannot price client work solely by multiplying hours by employee salary. Low billable utilization means fewer hours recover overhead. First measure actual capacity utilization, then calculate a project quote using loaded labor expense, subcontractors, overhead and a target selling-price margin.

A worked scenario

110 billed hours from 160 available hours; project uses 80 hours at $45 loaded labor cost, $1,000 contractors, $500 overhead and a 30% margin target.

Utilization: 68.75%; minimum cent-rounded project quote: $7,285.72.

Use loaded hourly labor cost, not the client billing rate, and document what is inside allocated overhead.

How to plan this decision

  1. Measure usable hours

    Track billed and available hours over the same time period.

  2. Define loaded project cost

    Include employer costs, contractors, direct tools and allocated overhead without duplication.

  3. Quote a target margin

    Distinguish margin from markup, then add a documented risk reserve if needed.

Read the detailed worked guide →

Start with the formula

Build a complete project cost, add contingency, and distinguish quoted margin from final realized profit.

Read How to Calculate Contract Profit and Protect Project Margin →